I reached out to NYS DOT last week with some questions about the ongoing 347 Greenway Project. There are 2 projects that will effect the B-Section. The first project is from Hallock Road to Nicholls Rd which has now underway. This project Will include sound barriers, but they will only be on 347, not on Nicholls Rd (yet). The second project will be the bridge at the 347/Nicholls Rd intersection. The plans for this are not yet determined but estimated to begin in 2028. My inquiry was to open the conversation about how the projects will effect the B-Section, including how we go about putting up neighborhood signs at the entrances. I have included photos of my email and their response here. I will be following up with them and will continue to keep you all updated. - Tim


 
 
 