I am getting a lot of questions regarding the Sound Barriers. For this phase of the project, sound barrier will start a little bit after the sump (between medical park and barker.) then will end at Barker (Entrance) and then start again where Bonnie starts, and run continuously all the way until it reaches roughly at the end of the property line for the second house on the right of Bonnie (14 Bonnie). The next phase which starts in 2028, the plan is not settled as of yet but they have a "Preferred Alternative" as they call it - and this plan if so chosen will have the sound barrier continue until the end of 26 Bonnie. The attached photo of the "Preferred Alternative" was taken from the S-Section "Circle of Friends" notice to its community regarding the same info. We all want to stay informed. I will be meeting with the State Inspector myself at some point and will present any questions you might have. Please email me any questions and I will see what I can do. - Tim


 
 
 